25. CONNECT FOLLOWING HOSES:
(a) EGR vacuum hose
(b) Fuel hose
(c) Actuator vacuum hose
(d) Brake booster vacuum hose
26. CONNECT FOLLOWING WIRES AND CABLES:
(a) Distributor connector
(b) High-tension cord from the ignition coil
(c) Oxygen sensor wire connector
(d) Ground strap to cylinder head cover
(e) Temp. switch wire (for A/T)
(f) Solenoid resistor connector
(g) Knock sensor wire connector
27. INSTALL ACCELERATOR AND ACTUATOR CABLE BRACKET TO CYLINDER HEAD COVER
28. INSTALL THROTTLE CABLE BRACKET TO CYLINDER HEAD COVER (for A/T)
29. FILL WITH COOLANT
Close the radiator and engine drain cocks and fill with coolant.
Total capacity: Dry fill
M/T 8.0 liters (8.5 US qts, 7.0 Imp. qts)
A/T 7.9 liters (8.3 US qts, 7.0 Imp. qts)
30. CONNECT CABLE TO NEGATIVE TERMINAL OF BATTERY
31. START ENGINE
Warm up the engine and check for leaks.
32. PERFORM ENGINE ADJUSTMENT
(a) Recheck the ignition timing. (See page IG-10)
(b) Retighten the cylinder head bolts.
(See step 3 on page EM-34)
33. ROAD TEST
Perform a road test.
34. RECHECK COOLANT AND ENGINE OIL LEVEL