SR-56
STEERING — Power Steering (Power Steering Pump)
9. INSTALL FLOW CONTROL VALVE AND SPRING
Insert the spring and valve into the housing.
10. INSTALL PRESSURE PORT UNION
Install and torque the union.
Torque: 700 kg-cm (51 ft-lb, 69 N-m)
11. INSTALL SUCTION PORT UNION
(a) Install a new O-ring in the union.
(b) Push in the union, and install the two bolts.
(c) Torque the two bolts.
Torque: 130 kg-cm (9 ft-lb, 13 N-m)
12. INSTALL AIR CONTROL VALVE
Torque: 370 kg-cm (27 ft-lb, 36 N-m)
13. INSTALL DRIVE BELT ADJUST STAY
Install and torque the two bolts.
Torque: 12 mm bolt 185 kg-cm (13 ft-lb, 18 N-m)
14 mm bolt 420 kg-cm (30 ft-lb, 41 N-m)