TSRM/MK4 Supra/Repair Manual
Repair ManualWiring Diagrams
p.113

ATTE/A340 Automatic Trans (GTE) — Inspection Procedure, page 114

114 / 118
p.115
Inspection Procedure — MK4 Supra A340 Automatic Trans (GTE), page 114
100%
Page text (OCR transcript)
AT2–114
A340E (2JZ—GTE) AUTOMATIC TRANSMISSION – TROUBLESHOOTING

INSPECTION PROCEDURE

1 Check voltage between terminal TE1 and E1 of DLC2 or DLC1.

C Measure voltage between terminals TE1 and E1 of DLC2 or DLC1.

OK Voltage: 4 — 6 V

TE1 E1

DLC2          DLC1

S-17-1 laj-23-1

NG

OK Proceed to next circuit inspection shown on matrix chart (See page AT2–64).

2 Check harness and connector between ECM and DLC2, DLC1 and body ground (See page IN–30).

OK

NG Repair or replace harness or connector.

Check and replace ECM.